In this article, I will explain How to

Calculate the Tasks count in Project Schedule in Project Server

Count All Tasks in Project Server

As shown above, the count of total tasks below the main Summary task is 6


Steps

  • Create an Enterprise Custom Fields.
  • Build the formula for the custom field.
  • Roll up the Calculation for Summary Rows.
  • Add the custom field to the appropriate Task View.
  • Edit your Project Schedule to calculate the formula.

Create an Enterprise Custom Fields

  • Open your PWA Site > PWA Settings.
  • Below the Enterprise Data > Click on Enterprise Custom Fields and Lookup Tables.
  • Click on New FIeld Button.
  • Set the appropriate name for your field “Tasks Count”.
  • At Entity, Select Tasks.
  • At Type, Select Number.

Calculate the Tasks count in Project Schedule in Project Server


Build the formula for the custom field

  • At Custom Attributes, choose formula.
  • In the formula text area, write the below formula

IIf([Summary], ([Task Count] - 1), 1)

In this formula, 

  • we checked if the current task is a summary task, calculates the task count, else show 1.
  • The [Task Count] is a built-in field that used to gets the total number of tasks.
  • The result of [Task Count] is always the number of tasks +1, so we use ([Task Count] – 1).

Calculate the total number of Tasks in Project Schedule in Project Server


Roll up the Calculation for Summary Rows

In this step, I will choose how this field gets rolled up for summary rows including grouping summaries by doing the following:

  • At Calculation for Summary Rows, choose Roll Up.
  • Select Count All to calculate the total number of tasks below each summary task.
  • Save your custom field.

Calculate the total number of Tasks in Project Schedule in Project Server


Add the custom field to the appropriate Task View

As we explained, this custom field is a task custom field that should be added to Task view like Task Summary view as the following.

  • Open PWA Settings, below Look and Feel > Select Manage Views.
  • Below Project Category > Click on Task Summary.
  • Below Fields, Select the newly created field, then click on add button to add it to the shown fields in this view.
  • You can move the field Up and down as you prefer.

Calculate the total number of Tasks in Project Schedule in Project Server


Edit your Project Schedule to calculate the formula

If you opened your project schedule, you will note that the formula is not calculated yet as shown below:

Calculate the total number of Tasks in Project Schedule in Project Server

To make the formula reflected and calculated properly, you must

  • Edit your Project Schedule.
  • Perform a specific edit as you need.
  • Click on Save, wait a moment until the Save operation completed successfully.
  • Click on Publish, wait a moment until the Publish operation completed successfully.
  • Then Click Close, to Check-in the Project.

Calculate the total number of Tasks in Project Server

Output

Get the total number of Tasks in Project Server


Applies To
  • Project Server 2016.
  • Project Server 2013.
  • Project Server 2010.
  • Project Online
See Also

In case, you need to get the total number of project in project center, check PROJECT CENTER TOTALIZE.

Advertisements

2 thoughts on “Count All Tasks in Project Server

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s