You can’t inactivate a task that’s in progress in Microsoft Project

In this hint, I will show How to set a task as inactive in Microsoft Project without facing the below issue.

You can’t inactivate a task that’s in progress

You can't inactivate a task that in progress


Scenario

Continue reading “You can’t inactivate a task that’s in progress in Microsoft Project”

Advertisements

Change the Project Manager of an Enterprise Project in Project Server 2013

I have a primary project manager for a whole project and multiple project managers who are responsible for managing the task updates and assignments within a project and are separate from the primary project manager.

  • The Primary Project Manager is called Owner.
  • Other Project Managers are called Status Manager.
    • The purpose of Status Manager?
      • This is particularly useful when different status managers are responsible for various aspects or phases of the project, or if the main Project Manager is absent or have a vacation, he can delegate another one as Status Manager to take ownership of the task assignments, so as to receive all status updates.

In this article, I will explain How to change the Project Manager of an Enterprise Project in Project Server 2013.by following the mentioned two steps below: Continue reading “Change the Project Manager of an Enterprise Project in Project Server 2013”

Edits will not be saved. Any Edits made to the enterprise global template items are only available during this session in Microsoft Project 2013

In Project Server 2013, I tried to open a project schedule via Microsoft Project 2013, and when I tried to add a new column to the default view, I got the following error:

Edits will not be saved. Any Edits made to the enterprise global template items are only available during this session

Edits will not be saved in Project 2013

Cause : Continue reading “Edits will not be saved. Any Edits made to the enterprise global template items are only available during this session in Microsoft Project 2013”

How to calculate %Complete Vs %Work Complete In Microsoft Project

In this article, I’m gonna answer the following questions:

  • What’s the difference between %Complete and %Work Complete?
  • What’s the difference between Actual Duration and Actual Work?
  • How the %Complete field is calculated in MS Project?
  • How the % Work Complete field is calculated in MS Project?

Continue reading “How to calculate %Complete Vs %Work Complete In Microsoft Project”