Change the Project Manager of an Enterprise Project in Project Server 2013

I have a primary project manager for a whole project and multiple project managers who are responsible for managing the task updates and assignments within a project and are separate from the primary project manager.

  • The Primary Project Manager is called Owner.
  • Other Project Managers are called Status Manager.
    • The purpose of Status Manager?
      • This is particularly useful when different status managers are responsible for various aspects or phases of the project, or if the main Project Manager is absent or have a vacation, he can delegate another one as Status Manager to take ownership of the task assignments, so as to receive all status updates.

In this article, I will explain How to change the Project Manager of an Enterprise Project in Project Server 2013.by following the mentioned two steps below: Continue reading Change the Project Manager of an Enterprise Project in Project Server 2013