Display the Task Hierarchy of a subtask within My Assignments view inside Tasks section in Project Server

I have been prepared a project schedule via Project Professional 2013, I tried to organize the tasks by indent the “Database Corrupted“task below “MSSQL” task.

task hierarchy 0

To looks like this.

task hierarchy 1

The task “Database Corrupted” has been assigned to a specific Team Member by Project Manager/Status Manager, when he was receiving his assigned task within Tasks section in PWA site.he couldn’t know what’s the hierarchy task for this subtask!

In this hint, I will elaborate How to display the Task Hierarchy of a subtask within My Assignments view inside Tasks section in Project Server as shown below.Tasks in PWA 1

Steps:
Continue reading Display the Task Hierarchy of a subtask within My Assignments view inside Tasks section in Project Server